Insight · risk management
The risk register nobody reads
A register with forty rows and no owner per row is not risk management. It is a document that proves someone was worried.
Open the risk register of almost any programme and you will find forty rows, a colour per row, and a review date that has already passed. It is a document that proves someone was worried. It is not a control.
The failure is structural. A register listing risks without owners, triggers or responses is a list of anxieties sorted by font size. Nothing in it tells you what to do on a Tuesday.
What a row needs before it earns its place
- An event, not a category. “Vendor risk” is a category. “The payment provider withdraws sandbox access before UAT, blocking certification for three weeks” is an event you can act on.
- A named owner. The person who would have to fix it, not the person who noticed it.
- A trigger. The observable signal that it is happening. “Two consecutive missed sandbox refreshes” beats “likelihood: medium”.
- A response chosen in advance. Accept, mitigate, transfer or avoid — and what that means concretely this month.
- A date the response is due. Without one, mitigation is an intention.
Five fields. A register with five fields and twelve rows is worth more than one with forty rows and none of them.
Why registers grow instead of working
Because adding a row is cheap and closing one is political. Nobody is thanked for removing a risk; somebody is blamed if it materialises after removal. So registers only grow, and the rows that matter drown.
The discipline that fixes this is brutal. Every risk carries a review date, and on that date it is either re-owned with a new response or closed with a sentence explaining why it is no longer a risk. No third option. A register where nothing closes is a register nobody trusts, and an untrusted register is not read.
The version that survives a programme
Keep the register to risks that would change a decision in the next sixty days. Everything else goes on a watch list with a trigger, and is promoted only when the trigger fires. This is not less rigorous. It is the only way the document stays short enough to be read in a steering meeting.
Then put the top three on one slide, with the response and the date. If the sponsor cannot tell you what they would do about the third one, that risk has no owner in the room — which is the most useful thing the register has told anyone all quarter.
Working through this now?
